Charles Edwards, Barrister and TECBAR Adjudicator reviews the Technology and Construction Court case of Grove Developments Ltd v S&T (UK) Ltd [2018] EWHC 123 (TCC), which provided much needed and useful guidance in relation to payments arising from construction contracts, in particular, Payment Notices and Pay Less Notices.
By way of background, on 26 March 2015, the parties entered into a contract incorporating the JCT Design and Build Contract 2011 (“the Contract”). The Claimant, Grove, engaged the Defendant, S&T to design and build a new hotel at Heathrow Terminal 4. The contract sum was agreed at £26,393,730.04. The completion date was 10 October 2016, however, Practical Completion in relation to the project was not achieved until 24 March 2017. There were three adjudications between the parties. The first adjudication decision concluded that the Schedule of Amendments was a part of the contract. The second adjudication decision concluded that S&T were entitled to an Extension of Time. The third Adjudication decision concluded that Grove’s Pay Less Notice of 18 April 2017 was invalid and therefore, S&T were entitled to be paid in excess of £14 million in accordance with interim application no. 22.
The Claimant contended that its Pay Less Notice complied with the requirements of Clause 4.10.2.1 of the Contract as it specified the basis of calculation albeit with reference to a detailed calculation of £1,407.748 in the purported Payment Notice dated 13 April 2017. The Defendant disagreed, that the document referred to in the Payment Notice dated 13 April 2017 should have been attached to the Pay Less Notice and therefore a reference to it was not sufficient to comply with the Contract.
The Claimant commenced CPR Part 8 proceedings for the Court to determine four separate issues:
“…
- Issue A: whether or not Grove’s Pay Less Notice complied with the requirements of the contract;
- Issue B: whether, even if the Pay Less Notice did comply with the contract, the result in the third adjudication in S&T’s favour should still be enforced;
- The fact that a dispute about the true value of the works in an interim application for payment can be adjudicated upon as the true value was not decided in the earlier adjudication about notices.
- Section 108(1) of the 1996 Construction Act provided:
- The dispute which the Employer wished to raise in the second adjudication would be different to that which was determined in the first adjudication. The issue to be determined in the first adjudication was whether or not there was a valid Payment Notice or Pay Less Notice or out of time and not the true value of the valuation.
- The contract expressly differentiates between “the sum due” (Clause 4.7.2) on the one hand, and “the sum stated as due” in the payment notice or the pay less notice (Clause 4.9), on the other. The contract deliberately uses different terms and in the Court’s view, the answer is obvious. “The sum due” is identified in Clause 4.7 because that is the result of the contractual mechanism designed to calculate the contractor’s precise entitlement (the ‘true’ valuation). It is the process by which the correct amount, calculated to the penny, is arrived at. That is a very different thing to “the sum stated as due”, which is the phrase used twice in Clause 4.9. Clause 4.9 recognises that the contractor’s application/payment notice will identify the sum which the contractor has “stated to be due” and it provides that, in the absence of a payment notice and/or a Pay Less Notice from the employer, it is “the sum stated as due” which will be payable. Similarly, if there was a valid pay less notice, then it would be “the sum stated as due” in that notice that would be payable. In neither case would it be the sum due and payable (“i.e. the true value”).
- The employer could refer the dispute about the true valuation to adjudication, once he had paid the sum stated to be due with regard to considerations of equality and fairness.
- The only real justification which had been advanced in the cases for prohibiting an employer from commencing a second adjudication, to deal with the dispute about the ‘true’ value, has been the mantra that it does not really matter, because the prohibition only applies to interim applications, and does not apply to the final application. As a matter of first principles, there seems to me to be nothing whatsoever to justify this different treatment. There is nothing in the Act or the Scheme which draws any such distinction: on the contrary, s.110A, s.110B and s.111 of the 1996 Act apply to both interim and final payments.
- Each has to make plain that it is, respectively, a payment notice or a pay less notice.
- Each has to clearly set out the sum which is said to be due and/or to be deducted; and
- The basis on which that sum is calculated.
Charles Edwin Edwards MSt(Cantab) MSc(Lond) FCInstCES Barrister
NEW TEMPLE CHAMBERS
2nd Floor Berkeley Square House
Berkeley Square
Mayfair
London W1J 6BD
Tel: +44(0)207 887 6098